Date |
Milestone |
notes |
---|---|---|
now–mid-July, 2011 |
Jiras created and assigned for all v1.8 customization work |
who should do what work? |
mid–late July, 2011 |
Work on closing assigned Jiras |
|
late July, 2011 |
Deploy a partially customized version of CollectionSpace 1.8 |
emphasis will be on functionality and customizations. |
July 26-29, 2011 |
First of two sprints to finish data mapping |
|
August 9, 2011 |
Director has requested staff-wide demonstration of PAHMA-CSpace 1.8 |
45-minute presentation |
August 16-19, 2011 |
Second of two sprints to finish data mapping |
|
mid-August, 2011 |
User testing of customized v1.8 |
|
September, 2011 |
Further customization of 1.8 according to outcome of user testing |
iterative adjustments will be made according to user feedback |
late October, 2011 |
Deploy a more fully customized version of CollectionSpace (based on v1.11 |
includes: |
November, 2011 |
User training for Museum staff |
includes: |
mid-December, 2011 |
Deploy CollectionSpace 2.0 |
Final pre-migration testing and tweaking |
mid-late December, 2011 |
Full migration of PAHMA data to CollectionSpace 2.0 |
includes: |