Timetable
Date | Milestone | notes |
---|---|---|
now-mid now–mid-July, 2011 | Jiras created and assigned for all v1.8 customization work | who should do what work? |
mid-late mid–late July, 2011 | Work on closing assigned Jiras |
|
late July, 2011 | Deploy a partially customized version of CollectionSpace 1.8 | emphasis will be on functionality and customizations. |
July 26-29, 2011 | First of two sprints to finish data mapping |
|
August 9, 2011 | Director has requested staff-wide demonstration of PAHMA-CSpace 1.8 | 45-minute presentation |
August 16-19, 2011 | Second of two sprints to finish data mapping |
|
mid-August, 2011 | User testing of customized v1.8 |
|
September, 2011 | Further customization of 1.8 according to outcome of user testing | iterative adjustments will be made according to user feedback |
late October, 2011 | Deploy a more fully customized version of CollectionSpace (based on v1.11 | includes: |
November, 2011 | User training for Museum staff | includes: |
mid-December, 2011 | Deploy CollectionSpace 2.0 | Final pre-migration testing and tweaking |
mid-late December, 2011 | Full migration of PAHMA data to CollectionSpace 2.0 | includes: |