- Perform post-launch support for the Bot Garden
- Ask Holly and Paul for feedback (May)
- Training for pot tag procedure and hort staff use (May)
- Determine whether we have performance problems, especially from the user perspective
- Assess impact of term completion changes in 3.2.2 (PAHMA-813)
- May 20: Repeat log analysis for term completion times (May)
- STIM: Team discussion on approach and set out new tasks (Chris, Ray, Glen, Rick, Aron) (May)
- Assess user experience of system performance: UCJEPS (2 hours - meet, identify and document pain points) (May)
- Assess user experience of system performance: PAHMA (2 hours - meet, identify and document pain points (May)
- Assess user experience of system performance: UCBG (2 hours - meet, identify and document pain points (May)
- Identify any June tasks that are high priority to address performance issues (May)
- Identify June tasks or changes (May)
- Assess impact of term completion changes in 3.2.2 (PAHMA-813)
- Address critical stability bugs for existing deployments
- Stability bug: Frequent re-initialization of app layer (authority search SWOD) (CSPACE-5988) (May)
- Stability bug: Report server failures, tomcat restart (CSPACE-5766) (May or June)
- Usability bug: Address side effects of term-completion changes that are making it difficult for users to find correct terms (CSPACE-6000 and CSPACE-6001) (May)
- Django-based web applications
- Finalize the framework (CSPACE-5981) (May)
- Document the approach, with examples (CSPACE-6002, CSPACE-5990) (May)
- Needs new styling: Build out Bot Garden reports that take parameters (UCBG-282) (May)
- Done: Build out PAHMA reports that take parameters (PAHMA-818) (May)
- Complete design and approach for larger functionality chunks (STIM discussion - Thursday, May 9, 3-4) (May)
- See functionality notes at UC Berkeley web applications
- Advanced search capabilities (e.g., modify advanced search to allow searching across related records, see STIM, UCJEPS-369)
- Displaying images
- Download search results into a file
- Initiate design work with UCJEPS and UCBG (UCJEPS-404) (May)
- Identify June tasks (May)
- Build prototype search interface (June)
- Decide how we want to host and operate deployed systems
- STIM kickoff Tuesday, May 7, 4-5 (May)
- Identify next steps and assign May and June tasks for following areas
- System administration
- Database administration
- dev-ops tools
- Develop process and SLA with customers to manage expectations and set priorities
- Hold conversations with UCJEPS, PAHMA, Bot Garden (June)
- Develop SLA regarding common and locally-specific requirements and process to handle requests (June)
- Conduct initial planning for next deployment
- Retrospective with team about Bot Garden migration (STIM/Discussion scheduled for June 6)
- Write up and identify improvements for next time (June)
- Selection (DAG, CH, PS) (May)
- Discuss approach to ... (DAG, CH, PS) (June)
- Project expectations/SLA
- Project methodology and management
- Functional fit-gap/design
- Data analysis/design
- Identify June tasks (May)
- Retrospective with team about Bot Garden migration (STIM/Discussion scheduled for June 6)
- Perform identified work for CollectionSpace 3.3 and Mellon Officers Grant -- see the v3.3 release page
- Unified config and other bug fixes (May)
- Contribute UCB customizations to project (Show Related Objects; Add to Record; maybe others) (May)
- Done. Upgrade UCJEPS to 3.2.2 (May)
- Make progress on Delphi integration for PAHMA
- What are goals for May and June -Â images, metadata?
- Incorporate Citation contribution from SMK
- Review, integrate (including modifying code/config as needed), and test contribution (CSPACE-6006) (May)
- Map SMK schema to PAHMA/TMS data (June)
Other irons in the fire
- MediaHandling-CollectionObject batch process for UCJEPS and PAHMA (May)
- Get backups going on dev.cspace (May)
- Move ucjeps-dev to UCB data center VM (May)
- BerkeleyMapper integration
- Geomancer integration
- Mellon Officers Grant UI/Fluid documentation tracking