CineFiles CollectionSpace Migration Timeline
July 2013
- Requirements
- Documenting existing system
August
- Requirements
- Data mapping
- Initial UI (user interface) design
September
- Data mapping
- UI design
- Initial data extraction and transformation
- Identify customizations
- System administration - setting up a machine to host CF in CS
- Start customizing CS code.
- Finalize scope (via fit-gap document)
October
- Continue customizing CS code
- Begin deeper level programming
- Continue data ET (extraction and transformation)
November
- First demo with subset of data and customization/functionality
- Continue Data ETL (extract, transform, load), customization, deeper programming
December
- Continue Data ETL (extract, transform, load), customization, deeper programming (including denorm tables and images)
- Add cf stats (http://www.mip.berkeley.edu/cgi-bin/cine_stats.pl) as well as use stats.
- Vacation!!
January 2014
- Meet to finalize Media Handling design and workflows
- Chris and Nancy to talk about IMLS grant to add stills and posters, etc.
- Continue Data ETL (extract, transform, load), customization, deeper programming (including denorm tables and images)
- Second demo with more data and subset of images
- Start work on reports: http://issues.collectionspace.org/browse/BAMPFA-67
- End January: Check in about Drupal project so we can decide what to do about CineFiles web site.
February
- Testing, revising and tweaking
- CineFiles website data testing
- CineFiles stats (http://www.mip.berkeley.edu/cgi-bin/cine_stats.pl) as well as use stats.
- Develop documentation and workflows
- Begin training
- Continue Data ETL (extract, transform, load), customization and deeper programming (including denorm tables and images)
- CineFiles stats page work (Django framework) See http://issues.collectionspace.org/browse/BAMPFA-107
March
First week:
- Launch and transition
- Freeze Sybase for a week (make accounts read-only), though Nancy OK with us freezing for longer if needed.Â